|
Over the past twenty (20) years, a great deal of confusion has
developed as to the difference between the term "Pay if Paid" and
"Pay when Paid". In fact the two phrases are used interchangeably
to such an extent, very few contractors or subcontractors are able
to distinguish between the two. Following the California State Supreme
Court decision in WM. R. Clarke Corporation v Safeco Insurance
Company of America Case, it is imperative that everyone understand
the difference between these two provisions and their relationship
to construction contracts.
Twenty five years ago, in Yamanishi v. Bailey & Collishaw, Inc.,
(1972) 29 Cal. App.3d 457, the California Appellate Court upheld
the Pay-when-Paid clause as valid and enforceable. However, the
court clearly stated the contractor may avoid payment for
a reasonable period of time only. In the Yamanishi
case, the contract contained a clause which indicated that the subcontractor
would be paid when the general contractor was paid by the owner.
The court analyzed this clause as determining the timing of payment
rather than creating a complete bar to payment if the owner never
paid the general contractor.
The question of what is a reasonable amount of time during which
payment may delayed is a question of fact which depends upon the
circumstances of each contracting situation. While many subcontractors
would like to have the question of reasonableness quantified more
precisely and frequently ask whether 60 days, 180 days or even one
year could be considered reasonable, this term simply defies black
and white answers and will turn on the factual situation and arguments
available in each separate case. The important point is - once a
reasonable time has passed, the contractor must pay the subcontractor
regardless of his receipt of funds from the owner.
The Yamanishi court indicated that a condition precedent
clause which actually barred the right to payment by the subcontractor
unless the general contractor was paid by the owner, would require
clear and express language to this effect in the contract. Thus,
the condition precedent or pay if paid wording frequently used today
developed out of the reasoning in the Yamanishi opinion.
On June 27, 1997, the California State Supreme Court invalidated
"Pay if Paid" clauses in construction subcontracts in California.
To quote the court:
"a general contractor's liability to a subcontractor for work performed
may not be made contingent on the owner's payment to the general
contractor..."
"We...conclude that a pay if paid provision is void because it
violates public policy that underlies the antiwaiver provisions
of the mechanic's lien laws."
As a result, the language frequently seen in construction subcontracts,
that payment to the general contractor is a condition precedent
to the general contractor's obligation to pay the subcontractor
for work preformed, is no longer enforceable in California. Additionally,
the court ruled that a payment bond surety may not claim the failure
of the owner to pay the general contractor for work, as a basis
for nonpayment to the subcontractor on payment bonds.
As quoted above, the basis for the court's holding that "pay-if-paid"
clauses in construction subcontracts are against public policy and
unenforceable stems from the indirect waiver or forfeiture of lien
rights in the event of nonpayment by the owner which could result
from enforcement of the clause. This contractual waiver is in contravention
to Civil Code §3262 which prohibits waiver of mechanic's liens without
payment and use of the appropriate statutory form.
The net effect of this recent California State Supreme Court decision
is the contractor must pay the subcontractor whether or not the
owner pays the contractor and regardless of what is in the contract.
All of the above can be stated simply: "Pay if Paid" or "Condition
Precedent" clauses which would relieve the general contractor of
its obligation to pay the subcontractor if the owner failed to pay
the general contractor are currently void and unenforceable. The
"Pay when Pay" clause is valid and allows the general contractor
to delay payment to the subcontractor for a "reasonable" time while
awaiting payment from the owner.
This article is intended to provide the reader with
general information regarding current legal issues It is not to
be construed as specific legal advice or as a substitute for the
need to seek competent legal advice on specific legal matters.
|