|
What exactly does a Release of Mechanic’s Lien release? Does it
release just the Mechanic’s Lien on file with the County Recorder
or the entire right to file a Mechanic’s Lien in relation to the
project? This issue has plagued construction practitioners for years.
Fortunately, a recent case has resulted in a practical answer which
is workable for all concerned parties.
In the recent case of Solit v Tokai Bank, (1-7-99) 81 Cal.Rptr.2d
243, the court held that a Release of Mechanic’s Lien only extinguished
the referenced Mechanic’s Lien and not the entire right to lien
the project. This case involved the construction of the Santa Monica
Beach Hotel owned by the Steins and financed by Tokai Bank. A dispute
arose between the Steins and the project construction manager, Mark
Solit. The first Mechanic’s Lien was recorded by Mr. Solit on March
7, 1990; however, no action to foreclose the Mechanic’s Lien was
brought within the 90 day statutory period and thus the lien became
void and unenforceable.
In August, 1990, the Steins’ attorney demanded that Mr. Solit release
his lien voluntarily or be subject to a petition under Civil Code
section 3154 ordering the release of the lien. After the demand,
Mr. Solit voluntarily executed a Release of Mechanic’s Lien referencing
the March 7, 1990 lien, but subsequently recorded a second Mechanic’s
Lien on October 22, 1990.
An action was filed between the Steins, Tokai and Solit. In the
action, Solit sought to enforce his lien of October 22, 1990 (although
there was some confusion in the complaint which made it appear that
Solit was attempting to foreclose on the March 7, 1990 lien). The
trial Court ruled that as a matter of law "Solit’s release of the
March 7, 1990 lien extinguished all of Solit’s lien rights against
the property, thus making any subsequent liens, including the October
22, 1990 lien unenforceable." Based on this ruling, the Court dismissed
Solit’s complaint to foreclose the Mechanic’s Lien, and Solit appealed
this decision.
The Appellate Court concluded that Solit’s voluntary release of
the stale lien affected only the recorded lien and not his right
to record a subsequent lien. The right to record a lien, for the
same work and materials released in the original lien, is still
limited by the time constraints which control the recording of any
lien. The Court balanced the rights of owners verses those of contractors
in making its decision. The Court commented that in allowing a Release
of Mechanic’s Lien to only release the particular recorded lien,
and not the constitutional lien rights of the contractor, provided
a fair balance between claimants and owners. To hold otherwise the
Court noted, would unfairly favor the owners in that they would
receive a windfall if a contractor filed a lien early and was forced
to release that lien or have it removed by the court upon the owner’s
petition.
To explain why the Solit case was necessary and the confusion that
previously existed in the construction industry, we have to look
back at the case of Maris Management Corp. v. Assured Drywall &
Textures, (1984) 152 Cal.App.3d 268. In that case, the court held
that if a stale Mechanic’s Lien was released by the court after
a petition brought by the owner, then not only was the recorded
lien released, but also the claimant’s right to file a lien for
that same work and materials was also released. Thus, the holding
of the Maris court lead many practitioners to believe that if a
contractor had its lien released through a petition of the owner
and/or voluntarily recorded a release of lien, then it was releasing
all right to a lien for that project. The Court in Solit addressed
the Maris decision and concluded that it was wrongly decided. Upon
reconsidering this important issue the Court held that a release
of a particular lien is simply just that, a release of that lien.
This decision is important for all contractors as it provides clear
guidance regarding the use of Release of Mechanic’s Lien forms.
The Solit decision allows the early contractor some time to negotiate
with the owner after the lien is filed, and if the statutory time
period for filing of a new lien is still open, the original lien
may be allowed to lapse or be released without waiving the right
to lien the project. The Solit case provides a greater opportunity
for negotiation and settlement rather than forcing early litigation
on a project. Based on the Solit case, to release or not to release
is an easier questions to answer and is now based solely on the
statutory time frames which have always governed the Mechanic’s
Lien rights.
This article is intended to provide the reader with
general information regarding current legal issues. It is not to
be construed as specific legal advice or as a substitute for the
need to seek competent legal advice on specific legal matters.
|